A small dollar change with a long schedule extension

Kern's proposed second amendment with Wallace & Associates adds $5,000 to an original $59,974 agreement, producing a new not-to-exceed amount of $64,974. That is an 8.34% increase.

More consequentially, it moves the end date from October 1, 2026 to June 30, 2027. Supervisors received the retroactive request on November 17—47 days after the prior term ended.

Adventure Play Area design agreement
MeasureValue
Original ceiling$59,974
Added authority$5,000
New ceiling$64,974
New end dateJune 30, 2027
Sources: Hart Park design amendment packet

The added work is specific

The amendment adds programmable-logic-controller coordination, specifications and an order of operations, plus project-management time. The county says Wallace will absorb some time in good faith because of design-team delays.

The payment schedule assigns 6% to project management, 23% to pump redesign, 14% to irrigation redesign, 31% to the PG&E application and 26% to construction assistance. That detail helps define work, although the packet does not show completion percentages or explain why the extension was not approved before October 1.

Retroactivity is the accountability issue

The record does not show that services were performed unlawfully or that the consultant caused the administrative delay. It does show that public approval followed the prior deadline and that the project schedule moved by nine months.

The Scoop reconciled the ceiling, percentage increase and dates. A closeout should list deliverables, invoice dates, PG&E status and the construction-start decision so the public can distinguish a design delay from a stalled capital project.