The amendment adds $763,573.72

Bakersfield's staff report says Ordiz-Melby Architects began with a $100,000 agreement for tenant-improvement work tied to the Police Department's move into Truxtun Tower. The amendment raises that ceiling to $863,573.72—an increase of $763,573.72, or about 763.6% of the original amount.

The council previously allocated $1.1 million for the tenant-improvement effort. The revised design contract alone equals about 78.5% of that allocation, leaving $236,426.28 before any other costs charged against the same allocation. The page does not provide a complete project budget.

Published contract and allocation figures
MeasureAmount
Original agreement$100,000.00
Increase$763,573.72
Revised ceiling$863,573.72
Prior allocation$1,100,000.00
Allocation less revised ceiling$236,426.28
Sources: Bakersfield November 18 agenda, Truxtun Tower item

The schedule warning lacks a dollar denominator

Staff said the Police Department must complete its move by the end of January 2027 or monthly expenses will exceed its current budget. The public item does not quantify that monthly overage, identify the expiring cost, or show the revised construction and move schedule.

That omission prevents a basic tradeoff test: whether the larger design amendment is cheaper than the cost of delay. The record supports urgency, but not a calculation of the break-even date.

A project dashboard could answer the remaining questions

The city should publish the complete tenant-improvement budget, committed costs by contract, construction contingency, planned occupancy date and monthly delay exposure. Design, construction, furniture, information technology and moving costs should be separated.

This analysis does not claim the amendment is excessive or unauthorized. It establishes the scale of the increase and the missing denominators needed to judge it.