Eight rows add to the reported $621,000
What's the Scoop With Broach recalculated Bakersfield's November 18 department-agreement report. The eight listed maximum amounts sum to $621,000, matching the total printed in the record. But the report's title says it covers agreements over $40,000 and under $100,000, while three rows are exactly $100,000.
Those three entries are Cimco Refrigeration, Granite Construction Company and Marderosian & Cohen. The other maximums are $40,000, $40,000, $50,000, $95,000 and $96,000. The arithmetic reconciles; the stated scope does not.
| Maximum | Number of rows | Combined |
|---|---|---|
| $40,000 | 2 | $80,000 |
| $50,000 | 1 | $50,000 |
| $95,000–$96,000 | 2 | $191,000 |
| Exactly $100,000 | 3 | $300,000 |
| Total | 8 | $621,000 |
A threshold label controls what readers think is included
A contract at the ceiling is not a trivial typographical detail when the document is a disclosure mechanism organized by value. If exactly-$100,000 agreements belong in the report, the label should say so. If they do not, the table needs correction or an explanation of a different threshold rule.
The record does not show that any listed agreement was improper. It establishes a mismatch between the declared range and three rows, not a finding about performance, procurement method or payments actually made.
What should be added to the next ledger
A durable agreement ledger would publish the exact inclusion rule, original and amended ceilings, procurement method, term, department, and a link to each executed agreement. That would let residents distinguish a one-time authorization from actual spending and identify amendments that cross a reporting threshold.
The immediate accountability question is simple: did the heading omit 'up to and including,' or were three contracts placed in the wrong report? A corrected title or annotated table would resolve it without changing the underlying eight-agreement total.