Evaluation passed; delegated approval did not
TVA's inspector general reviewed a sample of 35 investment-credit projects from a population of 650 projects executed in 2022–2025 with more than $1.9 billion in cumulative awards. All 35 were evaluated under established guidance, but 27 were not approved at the level required by TVA's delegation rules.
The eight sampled projects above $50 million received Economic Development Board and CEO review. The 27 below $50 million were not approved by the senior vice president or director specified in policy; those officials instead relied on staff.
| Group | Projects | Approval result |
|---|---|---|
| At least $50 million | 8 | Required approval completed |
| Below $50 million | 27 | Required level not documented |
| Total sample | 35 | All evaluated |
| Population | 650 | More than $1.9 billion |
A 77.1% sample exception rate is not a population rate
Twenty-seven exceptions among 35 sampled projects equal 77.1%, but the public summary does not say the sample was statistically representative. It would be wrong to project that percentage to all 650 projects or $1.9 billion.
The audit also reports no questioned costs and no funds recommended for better use. The finding concerns approval authority and policy alignment, not a determination that incentives were ineligible.
Three open recommendations create a measurable fix
The inspector general asked TVA to enforce the proper approval levels, update the outdated process document and align it with the Economic Development Board charter. All three recommendations remain listed as open.
Future closure evidence should identify who approved each project, under which threshold and on what date—without treating an after-the-fact signature as proof of timely review.