A minority of projects takes most construction funding
Twenty projects account for $466.7 million of the Indian Health Service’s $651.5 million fiscal 2026 allocation for ready-to-fund sanitation projects. They make up 35.7% of the 56 projects but consume 71.6% of that funding, according to a newsroom calculation from the agency’s April allocation letter.
IHS classifies those 20 projects as economically infeasible, meaning their estimated cost per eligible home exceeds an area-specific threshold. The label does not mean the projects lack public-health value or are prohibited. Congress specifically permitted infrastructure-law funding to reach costly projects that earlier annual appropriations rarely financed.
A comparison with the inspector general’s September tables shows the stakes of that decision: progress measured by dollars can look very different from progress measured by projects or households. The remaining work includes communities that lack basic water and sewage services, and expensive construction can produce a smaller household count without demonstrating waste.
Alaska’s funding share and household share diverge
For fiscal years 2022–2025, OIG’s Table 5 attributes $1,476,845,852 in Tier 1 funding to the Alaska Area and identifies 12,386 eligible homes expected to benefit. Compared with the national totals, that is 58.9% of funding and 11.4% of homes. The Great Plains Area shows the reverse: $166,529,671, or 6.6% of funding, for 35,727 homes, or 32.7% of the total.
The inspector general reports average costs of $119,235 per eligible home in Alaska and $4,661 in the Great Plains. These are funding allocations divided by homes expected to benefit, not household bills or a controlled comparison of contractor efficiency. The report identifies remote locations, low population density, harsh climates and difficult subsurface conditions among the reasons high-cost projects cluster in Alaska and the Navajo Area.
The year-by-year comparison also changes sharply. Dividing OIG’s Tier 1 funding by the corresponding expected household counts gives about $9,430 per home for the 2022 cohort and $45,278 for 2025—a 4.8-fold difference. Different project mixes, scopes and service needs prevent interpreting that ratio as a construction-price inflation rate.
More funding reaches the most severe deficiencies
OIG’s deficiency-level table helps explain the changing mix. In 2022, $93.9 million of $639.5 million in Tier 1 eligible project costs addressed level-5 deficiencies: communities lacking both a safe water supply and sewage disposal system. By 2025, that category accounted for $451.6 million of $652.6 million. The report rounds the shares to 15% and 69%.
IHS told auditors that it funded all ready-to-fund level-2 through level-5 projects in the first year, leaving subsequent rounds tilted toward more complex, costly work. The 2026 allocation letter says funding decisions continue to prioritize legacy projects that have completed planning, reflecting recommendations gathered through earlier tribal consultation.
That priority carries a practical qualification. Ready to fund does not mean ready to break ground. The letter says design and construction documents must still be finalized before procurement can begin. It allocates $630.1 million to construction and $21.4 million to design and construction documents, together forming the $651.5 million used in this comparison.
Funding decisions still depend on design and partners
The 2026 Tier 1 projects also include $75.4 million in costs IHS cannot pay with its appropriations, including portions serving noneligible homes, businesses and public institutions. The agency says it works with tribes and other funding partners to identify those resources. The letter does not establish that every partner contribution had been secured or that every funded project had entered construction.
OIG found staffing, contractor availability, cost-estimation and procurement problems affecting delivery. But its records also document completed work: 119 projects serving 20,247 eligible homes by October 2025. These completion figures have an earlier cutoff than the 2026 allocation and should not be substituted for a current progress count.
The oversight test is therefore more specific than whether one region gets a large share or whether fewer projects receive funding. Readers need to know which funded projects have finished design, secured their non-IHS contributions and delivered usable systems. The public records examined here explain the allocation strategy and its constraints; they do not provide that current project-by-project completion accounting.