A $1,000,291 increase
Kern Public Works asked supervisors to replace a 2023 Level 3/Lumen agreement for relocating telecommunications facilities at the Atlas Street grade separation. The former estimate was $377,727.70; the new agreement is $1,378,019.13.
The difference is $1,000,291.43. The new amount is 3.65 times the old estimate, and the increase alone equals 264.8% of the earlier figure. Road Fund money would reimburse the utility for eligible relocation work.
| Version | Amount |
|---|---|
| Earlier estimate | $377,727.70 |
| Replacement estimate | $1,378,019.13 |
| Increase | $1,000,291.43 |
| New amount as multiple of old | 3.65× |
The original estimate omitted whole cost categories
The board letter says the 2021 estimate did not include labor and material escalation, conduit, cables, pull boxes, accessories or Frontier's telecommunications cables. That explanation is concrete counterevidence to any suggestion that the increase is unexplained.
It also exposes an estimating-control problem: multiple predictable categories were outside the baseline used for the earlier agreement. The packet does not break the extra $1 million among inflation, added assets, design change and the second carrier, so the public cannot identify the dominant cause.
This is an estimate revision, not proof of payment
The Scoop compared the two authorized estimates and calculated the increase and multiple. The records establish a superseding reimbursement agreement and the reasons staff listed; they do not establish that $1.38 million has been paid or that Lumen caused the original omissions.
A closeout should publish quantities, unit prices, actual invoices, Frontier's share and any unused authorization. That would show whether the revised estimate corrected the baseline or created a new ceiling that actual work never reached.
Sources and further reading
Kern County November 17 agenda ↗